Concrete paving continues on 38th Avenue east of Wadsworth. All turn movements are possible at the Wadsworth / 38th Avenue intersection. Some travel delay is expected due to lane closures approaching the intersection.
Driveway, sidewalk, curb and gutter concrete paving is underway along northbound Wadsworth between 38th and 41st avenues. Northbound daily single lane closures will continue as needed.
Crews are working on the retaining wall system along southbound Wadsworth south of I-70. Landscaping and lighting continue throughout the project.
47th Avenue west of Wadsworth Avenue reopened last week after final concrete and asphalt work.
All work is weather-dependent, and construction schedules are subject to change.
Questions or concerns? Hotline 303-390-0878 or email WadsworthProject@ci.wheatridge.co.us
Visit What's Up Wheat Ridge for more information.