Wadsworth Improvement Project

Wadsworth Project Design Photo

Weather-permitting, 38th Avenue is currently on schedule to reopen east of Wadsworth Boulevard on the morning of Monday, April 8. All turn movements at the intersection will be possible. 38th Avenue traffic will be in a temporary alignment with a reduced number of lanes to accommodate ongoing construction on 38th as part of the Wadsworth project.

Some travel delay is expected due to lane closures approaching the intersection. Alternate routes are advised while construction continues for at least the next month on the east side of the intersection.

Next week, concrete paving will continue on northbound Wadsworth near 38th Avenue.

All work is weather-dependent, and construction schedules are subject to change.

Questions or concerns? Hotline 303-390-0878 or email WadsworthProject@ci.wheatridge.co.us

Visit What's Up Wheat Ridge for more information.

Facebook Twitter Email

Other News in Happening in Wheat Ridge

Wheat Ridge City Plan

Posted on: April 22, 2024
Photo of a chair on grass

2024 Large Item Pick-up Program

Posted on: March 28, 2024
Jefferson Center for Mental Health Logo

Mental Health and Wellness Series

Posted on: January 29, 2024 | Last Modified on: March 14, 2024
City of Wheat Ridge Projects and Properties Map Newsflash

New Projects and Properties Map

Posted on: December 19, 2023